Before you dig, the law requires asking the utility owners to locate their lines. But locates only protect you if you read them right. Locate marks use a uniform color code with eight colors, though a state may specify other colors. Six mark types of buried line, and two mark something other than a line.
The Color Code
Respect every color. Here is what each one means. Yellow marks gas, oil, steam, petroleum or gaseous materials. Red marks electric power and lighting lines. Orange marks communication, alarm or signal lines. Blue marks drinking water. Green marks sewers and drain lines. Purple marks reclaimed water, irrigation and slurry lines. Pink marks temporary survey markings. And white marks the proposed excavation: your dig. If your dig site can't be clearly described on the locate ticket, it's a good habit to mark the route or area to be dug in white. Do it on site, or electronically where your 811 center offers it, before or during the locate request.
Offsets
A good habit when you read the marks: remember a mark is not always on top of the line. Where site conditions make it hard to mark the line or keep a mark on it, locators may use offset marks, together with marks over the line when they can. And as digging gets close to where a line is estimated to be, the law requires finding its exact location by safe and acceptable means. If a surface feature used for offsets is changed or moved, it's wise to treat that part of the locate as no longer valid and get it re-marked.
Keep the Marks Good
It's recommended to protect and preserve the marks until they're no longer needed for safe digging. If a mark is removed or can no longer be seen, the recommended step is to stop digging and ask 811 for a re-mark. Best practice: photograph the marks before digging, as a record. A photo never replaces the marks on the ground. Near a pipeline, the law requires calling 811 again as needed, so it's located and marked before you dig.
Recap
To recap. Good habits: if your dig can't be clearly described on the ticket, mark it in white. Remember a mark may be an offset, not on top of the line. Protect the marks; if one is removed or can't be seen, stop digging and ask 811 for a re-mark. In short: yellow is gas, oil, steam and petroleum, red is power, orange is communications, alarm and signal lines, blue is drinking water, green is sewers and drains, purple is reclaimed water, irrigation and slurry. And close to a marked line, find its exact location by safe means before you dig on.
Sources
- US OSHA excavation standard (29 CFR 1926 Subpart P)
- US PHMSA pipeline damage prevention rules (49 CFR Part 196)
- Florida underground facility damage prevention law (an example of a state 811 law)
- Common Ground Alliance (CGA) Best Practices
- Dashpot recommended practice (said as such in the video)
This video is for work in the United States. It covers federal OSHA requirements and good practice, and the narration says which is which. States with their own OSHA-approved plans, and each state's 811 law, can set different or stricter rules. Rules also differ in Canada. General information only, not legal advice. Always follow federal and state regulations, your employer's procedures and the instructions of a competent person on your site. Narration is AI-generated (the Dashpot narrator voice); every script is checked against the sources listed above before it is voiced.
Dashpot checks that every worker on your crew understood the hazards and controls for the day's work. See how it works.